Second Annual Kurdistan DBX International Tradeshow,
Suleimaniya, November 11th – 14th,
building. |
This year IACCI is planning for the
second DBX Kurdistan will be held in
Suleimaniya in November this year
“Second Annual Kurdistan DBX
Tradeshow, November 11th – 14th,
Suleimaniya, Kurdistan, Iraq” to
show the world the will of Iraqis to
build their new
future. Suleimaniya was chosen to be
the place of event since Suleimaniya
is predominantly a Kurdish city, and
has been a centre for Kurdish
nationalism. The City is located in
northeastern Iraq with 700,000
inhabitants (2005 estimate).
Suleimaniya is the capital of the
governorate with the same name, and
part of the Kurdish Autonomous
Region.
Suleimaniya has since long been a
popular tourist destination among
Iraqis and Arabs visiting the city.
A new airport has been found
recently to link the city with the
world it lives in.
غرفة التجارة و الصناعة العراقية
الامريكية تخطط لتنظيم معرض كردستان
الدولي الثاني في السليمانية هذا
العام للفترة من 11-14 تشرين الثاني
كي تظهر للعالم ارادة العراقيين و
رغبتهم في بناء مستقبلهم الزاهر.
مدينة السليمانية هذه هي مدينة كردية
في الغالب و تعتبر مركزاً للقومية
الكردية. تقع الى الشمال الشرقي من
العراق و يبلغ عدد سكانها 700 ألف
نسمة حسب توقعات عام 2005. و هي عاصمة
محافظة السليمانية و جزء مهم من اقليم
كردستان. و منذ وقت طويل كانت
السليمانية مدينة يقصدها الزوار من
مختلف انحاء العالم. و قد تم بناء
مطار دولي فيها مؤخراً لربطها بدول
العالم الآخرى.
|
|
23/
10 / 2006 |
Finish
setup of both for hall four
The progress 85%
SEE PHOTO GALLERY |
|
21/
10 / 2006 |
start
to setup both
The progress 81%
SEE PHOTO GALLERY |
|
26/
9 / 2006 |
Complete with setup the Hall Selling with
sandwich Panel , The progress for
this day is 65%.
SEE PHOTO GALLERY |
|
21/
9 / 2006 |
Continue
with setup the Hall Selling with
sandwich Panel , The progress for
this day is 60%.
SEE PHOTO GALLERY |
|
14/
9 / 2006 |
Complete
installation for the Steel
Structure, Complete Fabrication of
Electrical boards, cable trench, and
inside lighting for the building, The
progress for this day is 51%.
SEE PHOTO GALLERY |
|
23/ 7 / 2006 |
work
in Cut and Fill process, The progress %
for this day is18%
SEE PHOTO GALLERY |
|
22
/ 7 / 2006 |
the
land of the project become more level
The progress % for this day is17%
SEE PHOTO GALLERY |
|
20
/ 7 / 2006 |
work
in Cut and Fill process, The progress %
for this day is16%
SEE PHOTO GALLERY |
|
19/ 7 / 2006 |
work
in Cut and Fill process. The progress %
for this day is15%
SEE PHOTO GALLERY |
|
18
/ 7 / 2006 |
work
in Cut and Fill process. The progress %
for this day is14%
SEE PHOTO GALLERY |
|
17 / 7 / 2006 |
discuses
the drawing for the Electrical work and
wiring. The progress % for this
day is13%
SEE PHOTO GALLERY |
|
16 / 7 / 2006 |
Finished
the steel Fabrication. The progress %
for this day is12%
SEE PHOTO GALLERY |
|
15/ 7 / 2006 |
Start
paint the columns The progress %
for this day is11%
SEE PHOTO GALLERY |
|
13/ 7 / 2006 |
start
work for the electrical Item The
progress % for this day is9%
SEE PHOTO GALLERY |
|
12 / 7 /2006 |
visit
the site today including the Chief of
Suleimaniya Police and others manager
department in local government. The
progress % for this day is8%
SEE PHOTO GALLERY |
|
11 / 7 / 2006 |
order
the Exhaust Fan (roof type)&the inside
lighting The progress % for this
day is7%
SEE PHOTO GALLERY |
|
10 / 7 / 2006 |
Meeting
with the Electricity Department The
progress % for this day is5%
SEE PHOTO GALLERY |
|
9 / 7 / 2006 |
Start
the Steel fabrication, The progress %
for this day is4%
SEE PHOTO GALLERY |
|
8 / 7 / 2006
|
20
of labors arrive to the site. The
progress % for this day is3%
SEE PHOTO GALLERY |
|
6 / 7 / 2006 |
starting
Cut the high level area. The progress %
for this day is2%
SEE PHOTO GALLERY |
|
5 / 7 / 2006 |
start
work. The progress % for this day is 1%.
SEE PHOTO GALLERY |